Bringing Electric Power to Hill Country Acreage: Who Pays, Overhead or Underground, and the Timeline

By Bethany Jenkins10 min read

Aerial of a Hill Country home of stone and wood with dark metal roofs among live oaks, a long gravel drive curving in from open pasture, and wooded hills beyond

You have found the land, and the nearest pole is a long way from where the house wants to sit. Before the pad is set, find out who serves the parcel, what that utility makes you do before it designs a line, and who pays for it. The whole-land picture, from county permits to water, is in our guide to building on your own land in Texas.

Quick answer: find your provider by address first, because Pedernales Electric Cooperative (PEC) does not serve every Hill Country parcel. PEC is not obligated to design until the house location is staked, and its tariff, effective October 1, 2026, includes one design and charges $500 or actual cost, whichever is greater, for a redesign. PEC publishes no per-foot rate and we found no construction allowance in the tariff: the applicant pays PEC’s Cost Calculation before construction and is billed for any cost above it. Bluebonnet’s tariff, effective July 1, 2023, charges for estimated line extension costs above $1,950 per service. PEC’s underground service is by agreement, and the member trenches. Its 90-day construction target starts after you meet all its requirements.

Find Your Provider by Address

Texas has no single power company for the Hill Country. Austin Energy, a municipal utility, serves parts of Travis County. Central Texas Electric Cooperative (CTEC) lists Llano, Kendall and Blanco among its counties, and Bandera Electric Cooperative serves parts of Kendall. Bluebonnet Electric Cooperative serves parts of Travis and Hays. PEC’s tariff says it may serve all or a portion of Blanco, Burnet, Comal, Hays, Kendall, Llano and Travis counties.

The Public Utility Commission publishes service area layers marked unofficial; the official boundaries are county maps on file with the commission. Use the layers to decide whom to call, then ask that utility, by address, whether it serves the building site.

The rest of this post follows PEC, because its process is public and dated: its Tariff and Business Rules for Electric Service (effective October 1, 2026), its page for individual locations and its underground installation specifications (September 11, 2026), as we read them on November 2, 2026.

House with a dark standing-seam metal roof and limestone walls seen across open grass between two live oaks at sunset

What PEC Needs Staked Before It Designs

PEC’s page for individual locations starts with a requirement that shapes everything after it: “A proposed dwelling location must be determined and staked.” PEC also asks for survey points, marked septic and drain fields where they apply, a site plan with utilities, a one-line electrical diagram, the 911 address and the deed. PEC says it is not obligated to provide a design or cost estimate until those items are in.

The sequence after that: you apply at the nearest PEC district planning office; PEC meets you at the site; once the design is done, PEC sends the cost estimate, the easement forms, any underground agreement and the design prints; you pay; PEC does a final review, builds, sets the meter and energizes the service once its requirements are met (its page notes some areas require city inspections first). The tariff effective October 1, 2026 lists a $50 establishment fee and a $200 system impact fee, which is in addition to any amount due for the line, plus a $50 membership fee for new members.

Who Pays: A Cost With No Per-Foot Rate

Asked on its own page for an average cost per foot or per pole, PEC answers that there are “many variables to be considered in an electrical design,” with the estimate provided “once the account is set up and a field meeting has taken place.”

Under Section 400.2 of the tariff, PEC determines a Cost Calculation “based on its then current unit material and labor costs,” and the applicant pays the cost to extend service to the point of interconnection, including poles, transformers and conductors, before construction begins. PEC’s page says “a new member/developer pays all costs to connect service to the PEC distribution system.” We found no construction allowance in the October 1, 2026 tariff. The payment is not refundable after construction, PEC keeps ownership of its facilities even though you paid for them, and any cost above the Cost Calculation is billed to the applicant.

So the number comes from PEC’s estimate for your pad, and the tariff says that estimate may expire or be recalculated at PEC’s discretion. Bluebonnet’s tariff is different. Its Section III, effective July 1, 2023 and still the version posted on November 2, 2026, has applicants pay a non-refundable contribution “for all estimated line extension costs greater than $1,950 per service.” The Bluebonnet pages we read give no per-foot rate either.

Dusk view of a dark timber-clad house with lit glass walls and a long lawn with ground uplights in front

Pad Placement Is the Design Lever

PEC prices the Cost Calculation from unit material and labor, so we read a longer route, or one needing more clearing, as costing more. That makes the pad location the lever you control.

Our role is coordination: we set candidate pads against the geotechnical report, which describes the ground at the likely pad, and the survey, which records easements and setbacks, then have the pad you choose staked before PEC designs. One design is included, so moving the pad after PEC designs means a redesign fee of $500 or actual cost, whichever is greater (tariff effective October 1, 2026), and PEC says changes after design may affect the timeline.

Two more PEC rules narrow the choices. The route must be “reasonably accessible during all weather conditions” as PEC determines, and PEC will not install facilities “in areas deemed inaccessible or hazardous.” A pad beyond a creek crossing that floods may not get the route you want. PEC’s meter loop specifications also cap service from the transformer to the meter at 150 feet without PEC’s written approval, so plan the transformer and meter locations with the house.

Since PEC wants a route it can reach in all weather, the access drive is a natural candidate for the line, so the pad, the drive and the route get decided together. We cover the drive in our post on driveways, fire access and culverts.

The Easement and Clearing Are Yours

PEC generally builds inside private easements on its standard form, though it may use public utility easements or right-of-way at its discretion. Under Section 300.9.1, the applicant grants them and acquires any needed from adjacent landowners, at the applicant’s cost, so a route across a neighbor’s land starts with a conversation of yours. The applicant also clears the required easements on its property to PEC’s specifications; where PEC clears, the cost goes into the Cost Calculation. Ask PEC for the easement width at the site meeting.

The tariff bars structures, landscaping and other obstructions that interfere with PEC’s easements unless PEC approves them, and lists an Easement Obstruction Review Fee of $775 or actual cost, whichever is greater (effective October 1, 2026). What an easement is and what can sit on one is in our easements, setbacks and lot survey guide.

Daylight view across a large lawn to a gray timber-clad house with a dark pool and rooftop terrace, live oaks behind and a black fence at right

Overhead or Underground

PEC’s tariff does not promise underground service. Section 400.7 says underground lines “may, by agreement with the Cooperative, be provided,” and the tariff publishes no price premium for them. Ask PEC early and get the agreement in writing.

If PEC agrees, the applicant provides and installs the trench, backfill, conduit and the concrete pads for transformers and meter pedestals. PEC supplies the conductors, transformers, meter pedestals and switchgear, paid for through the Cost Calculation.

PEC’s specification calls for at least 30 inches from the top of primary conduit to sub-grade, 24 inches of cover over the conductor from the transformer to the meter, and a PEC inspection before backfill. With PEC’s approval, cover can be reduced by 6 inches for every 2 inches of 3,000 PSI concrete poured onto the conduit. The drawing does not mention limestone, so where the geotechnical report shows shallow rock, ask PEC’s planner and your excavator early whether PEC will approve that.

Converting later adds cost. Under Section 400.22.3, PEC may replace an overhead line with underground only if it finds reliability is not harmed, receives an easement at no cost and is paid in advance for removing the old line and the full cost of the new one. Raise it at the first site meeting, and judge both against the view: overhead brings poles and spans, so ask PEC what equipment an underground design would leave above ground.

Transformer, Meter, Loads and Construction Power

A pad-mounted transformer needs room. PEC’s drawing dated September 11, 2026 calls for a minimum of 10 feet of clear, level, unobstructed working space in front and 5 feet of clearance around the sides and back, and PEC may require bollards. Keep that apron clear of planting and pool equipment, away from the sight lines of the main rooms, and reachable by a service truck. PEC approves the meter location (Section 300.13.1), and the owner supplies the meter loop, built to PEC’s specifications and the National Electrical Code.

Service entrance size, solar and batteries are covered in our guide to Tesla Powerwall in a luxury home.

PEC publishes no three-phase process, lead time or price for a single residence, and its tariff encourages members to learn the phase and voltage available before buying equipment. Ask at the first meeting what runs on the nearest line, before you specify a barn, shop, well pump or large pool load. Several dwellings on one service is a load question covered in our family compound guide.

If construction runs on temporary service, Section 400.13 has the applicant pay 100 percent of the cost of installing and removing non-permanent service before work begins, and PEC’s temporary service sheets require district office approval before a temporary loop is installed.

Covered terrace with teak seating beside a pool, looking past a black cable fence to scattered oaks and open grass

The Timeline: Where the 90 Days Start

Section 400.1 says requests for new service requiring construction “should be completed within ninety (90) calendar days of fulfilling all applicable requirements,” unless a cause beyond PEC’s control intervenes or a different period is agreed. As we read it, that clock starts after your steps: the staked pad, easements, clearing, fees and payment of the Cost Calculation.

PEC publishes no design time. Its page says the time for the planning department to begin and complete designs “may vary depending on the district’s workload,” and that changes requested after design “may affect the project timeline and material availability.” So we cannot give you a number of months from application to energized meter, and we found no published source that gives one for a single home.

Several of these steps are yours, so start them early: geotechnical report and survey first, pad staked, easement conversations underway, then the application. Our luxury ranch and estate guide covers how long-haul infrastructure sits in a whole-project schedule.

Frequently Asked Questions

Who provides electric service to rural land in the Hill Country?

It depends on the address. Austin Energy serves parts of Travis County. Pedernales Electric Cooperative’s tariff lists Blanco, Burnet, Comal, Hays, Kendall, Llano and Travis among the counties it may serve in whole or part. Central Texas Electric Cooperative lists Llano, Kendall and Blanco among its counties, Bluebonnet Electric Cooperative serves parts of Travis and Hays, and Bandera Electric Cooperative serves parts of Kendall. The Public Utility Commission’s service area layers are marked unofficial, so confirm with the utility by address.

How much does it cost to bring electric service to rural land in Texas?

Pedernales Electric Cooperative (PEC) publishes no per-foot or per-pole rate. After you stake the house location and meet PEC at the site, it prepares a Cost Calculation. Under its tariff effective October 1, 2026, the applicant pays all of it before construction and is billed for any cost above it, plus the $50 establishment and $200 system impact fees and, for new members, a $50 membership fee.

Does the co-op pay any of the line?

We found no construction allowance in Pedernales Electric Cooperative’s tariff effective October 1, 2026, and its page says the new member pays all costs to connect. Bluebonnet Electric Cooperative’s tariff, effective July 1, 2023, has applicants pay a non-refundable contribution for estimated line extension costs above $1,950 per service.

How long does it take to get power to a new home site?

Pedernales Electric Cooperative’s tariff says new service requiring construction should be completed within 90 calendar days of your fulfilling all applicable requirements, unless delayed by a cause beyond its control or another period is agreed. It publishes no design time, which varies with the district’s workload, and your staked pad, easements, clearing and payment come first.

Can the line to my house be underground?

Only by agreement with Pedernales Electric Cooperative, under Section 400.7 of its tariff, and the applicant provides the trench, backfill, conduit and concrete pads. Converting an overhead line later requires the easements at no cost to PEC and advance payment for removing the line and for the full cost of the new underground one, and PEC decides whether reliability allows it.

What happens if I move the house after the co-op designs the line?

Pedernales Electric Cooperative (PEC) includes one design. A redesign carries a Planning Design or Redesign Fee of $500 or actual cost, whichever is greater, per the tariff effective October 1, 2026, and PEC may charge it in advance. PEC also says changes after design may affect the timeline and material availability.

If you own Hill Country acreage, or are weighing a parcel before you close, and want the pad, the drive and the power route planned by the team that will design and build the house, call (512) 402-9222 or start a conversation with our team.